West Bengal Pollution Control Board



Status of the project


Pollution Prevention and Waste Minimisation
of Small Scale Industries in Kolkata Metropolis Area

 

Mile Stones

  • Approval of the project by ICEF

May, 2001

  • Project signed formally

October 1, 2001

  • Public notice published in seven daily newspapers inviting the boiler and ceramic kilns operators for apply for financial assistance

November 12, 2001

  • Project Management Plan (PMP) Meetings involving all stakeholders
    • First PMP Meeting

May 21- 22, 2002

    • Second PMP Meeting

October 22, 2003

    • Third PMP Meeting

March 9-11, 16-17, 2005

    • Fourth PMP Meeting

March 6, 2006

  • Project Steering Committee (PSC) Meetings
    • First PSC Meeting

September 4, 2002

    • Second PSC Meeting

December 16, 2003

    • Third PSC Meeting

June 14, 2005

    • Fourth PSC Meeting

July 6, 2006

  • Training programme for small boiler operators
    • First training

September 25 – October 5, 2002

    • Second training

April 21-25, 2003

    • Third training

March 30 – April 6, 2004

    • Fourth training

November 2-6, 2004

  • Disbursement of Financial Assistance
    • First disbursement

December 2002

    • Second disbursement

June 2003

    • Third disbursement

August 2003

    • Fourth disbursement

October 2003

    • Fifth disbursement

December 2003

    • Sixth disbursement

February 2004

    • Seventh disbursement

April 2004

    • Eighth disbursement

May 2004

    • Ninth disbursement

June 2004

    • Tenth disbursement

August 2004

    • Eleventh disbursement

October 2004

    • Twelfth disbursement

December 2004

    • Thirteenth disbursement

February 2005

    • Fourteenth disbursement

April 2005

    • Fifteenth disbursement

July 2005

    • Sixteenth disbursement

November 2005

    • Seventeenth disbursement

January 2006

    • Eighteenth disbursement

September 2006

  • Public notice published in daily newspapers inviting the plastic reprocessing units for apply for financial assistance

July 11 2005

  • Social impact study of the project 'conversion of coal fired industries to oil fired ones' on the industry stakeholders and neighbourhood population

January 2006
(Executive Summary)

Announcements

  • Last date for distribution of application form for financial assistance

Closed

  • Last date for receipt of application form for financial assistance

Closed

  • Last date for receipt of necessary documents required for availing financial assistance

31.12.2006

Name of the first batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the second batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the third batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the fourth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the fifth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the sixth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the seventh batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the eighth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the ninth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the tenth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the eleventh batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the twelfth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the thirteenth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the fourteenth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the fifteenth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

Name of the sixteenth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

  • Durga Oil Industries
  • Galaxy Rubber Industries
  • Genuine Rubber Products
  • Gladstone Lyall Employees Industrial Co-operative Society Ltd.
  • M. K. Enterprise
  • R. C. Rubber Products
  • Sreepati Hosiery Mills (P) Ltd. (Factory No. 1)
  • Sreepati Hosiery Mills (P) Ltd. (Factory No. 2)
  • Techno Dyeing & Bleaching Works
  • Topsia Rubber Works

Name of the seventeenth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

  • Shyamashree Bleaching Works
  • Bengal Rubber & Plastic Works
  • Rekha Rubber Works
  • M. K. Rubber Industries
  • Al-Hind Rubber Industries
  • L. M. Products
  • Sonargaon Ceramics
  • Sagar Merchandise Private Limited
  • Rubber Equipment & Engineering Co. (Private) Ltd.
  • Waheguru Rubber Manufacturing Co. (P) Ltd.
  • Fona East Corporation

Name of the eighteenth batch of units who completed conversion of small coal fired boilers/ceramic kilns to oil/gas fired ones, complied with the statutory norms and became eligible and obtained financial assistance

  • Arco Ceramics
  • Associated Porcelain (P) Ltd.
  • The Women's Cooperative Industrial Home Ltd.
  • Elite India Rubber Products Private Limited
  • Bani Rubber Works Private Limited
  • National Industries
  • New Central Rubber Industries
  • L.N.S. Industries

 

Description of ICEF applicant units

Rubber Equipment & Engineering Co. (Private) Ltd.
  • Waheguru Rubber Manufacturing Co. (P) Ltd.
  • Fona East Corporation
  • >Number of units having small boilers within KMC

    = 213

    Number of units having small boilers beyond KMC but within KMA

    = 23

    Number of units having Ceramic Kilns within KMA

    = 24

    Total number of applications received in ICEF project

    = 260

     

    STATUS OF CONVERSION OF UNITS HAVING SMALL BOILERS WITHIN KMC UNDER ICEF PROJECT

    Total no. of ICEF applicants = 212 ##

    Sl. No.

    Status

    Number

    1

    No. of units which have completed conversion

    188

    2

    No. of units which are at various stages of conversion

    11

    3

    No. of closed units

    14

    TOTAL

    213

    ## - Units excluded after final scrutiny are not considered here

     

    STATUS OF CONVERSION OF CERAMIC KILNS UNDER ICEF PROJECT

    Total no. of ICEF applicants = 23

    Sl. No.

    Status

    Number

    1

    No. of units which have completed conversion

    21

    2

    No. of units without kiln

    2

    TOTAL

    23

     

    Last updated on 16.11.2006  