Considering the background situation as illustrated, the project was conceived and prepared to improve the overall environment of the Kolkata and its surrounding area. The project for facilitating changeover to cleaner fuel and construction of CETP were prepared after due consideration of dire necessity of financial assistance required to be provided to such stakeholders. The stakeholders were taken into confidence while preparing the project.


Project objectives

Financial assistance will be provided for


Target groups


Beneficiaries


Project budget

Total project cost = Rs. 16.49 crores

ICEF contribution = Rs. 4.80 crores

WBPCB = Rs. 4.18 crores

Stakeholders contribution = Rs. 7.51 crores


Status of the project

A Steering Committee consisting of representatives from State Government, WBPCB, ICEF, Industry Associations and academic institutions will review the status of the project time to time.

 