Financial
assistance
Pollution
Prevention and Waste Minimisation
of Small Scale
Industries in Kolkata Metropolis Area
Eligibility
criteria
- operating with coal fired small
boilers in Kolkata
Metropolitan area changing over to combustion
efficient cleaner fuel (oil or gas) fired ones;
- operating coal fired ceramic
kilns in Kolkata
Metropolitan area converting to combustion efficient
cleaner fuel (oil or gas) fired kilns.
- Galvanising units of Natabar
Paul Road, Howrah,installing a Common Effluent
Treatment Plant for treatment of liquid waste.
Steps for
financial assistance
[A] For coal
fired boiler operators who want to join the project
If you are in the
process of conversion of old boiler and want to join the project
- Fill up the form carefully and
submit the filled up form with necessary attachments
(List A) at an
earliest
- Finish the installation of new
cleaner fuel fired boiler or retrofitted boiler
- Demolish the old coalfired boiler
- Commission the cleaner fuel fired boiler
- Ensure full commissioning.
- Obtain the commissioning
Certificate from the suppliers
- Obtain full payment certificate
from the suppliers once the payment is completed
- Take photographs of the new
installation
If you have completed
the conversion of old boiler and want to join the project
- Obtain the commissioning
Certificate from the suppliers
- Obtain full payment certificate
from the suppliers once the payment is complete
- Ensure full commissioning
- Take photographs of the new
installation
- Demolish the old coalfired boiler
- Commission the cleaner fuel fired boiler
- Fill up the form carefully and
submit the filled up form with necessary attachments
(List C) at an
earliest
[B] For coal fired
Ceramic kiln operators who want to join the project
If you are in the
process of conversion of old kiln and want to join the project
- Collect Application form from Paribesh Bhawan, 2nd
Floor, Kolkata for accessing financial assistance from
ICEF project by 01.10.2005
- Fill up the form carefully and
submit the filled up form with necessaryattachments
(List A) at an
earliest
- Finish the installation of new
cleaner fuel fired kiln or retrofitted kiln
- Demolish the old coalfired kiln
- Commission the cleaner fuel fired kiln
- Ensure full commissioning
- Obtain the commissioning
Certificate from the suppliers
- Obtain full payment certificate(s)
from the suppliers once the payment is completed
- Take photographs of the new
installation
If you have completed
the conversion of old kiln and want to join the project
- Collect Application form from Paribesh Bhawan, 2nd
Floor, Kolkata for accessing financial assistance from
ICEF project by 01.10.2005
- Obtain the commissioning
Certificate from the suppliers
- Obtain full payment certificate(s)
from the suppliers once the payment is complete
- Ensure full commissioning
- Take photographs of the new
installation
- Demolish the old coalfired kiln
- Commission the cleaner fuel fired kiln
- Fill up the form carefully and
submit the filled up form with necessary attachments
(List C) at an
earliest
After receipt
of the properly filled up applications from the entrepreneurs
- The new installation/retrofieted
installation will be inspected by the Board officials
- The Project Scrutiny Committee will
scrutiny the papers submitted for the financial
assistance
- If Scrutiny Committee is satisfied
fund will be disbursed
Proposed Activity Schedule for the subproject for Emission Control device for Waste Plastic Reprocessors (excluding PVC manufacturers) operating in KMA under WBPCB ICEF project
- The unit shall submit the ‘Expression of Willingness to install the emission control device and obtain necessary regulatory permits’ through proper applications
- The Board shall process this applications and issue provisional permission to run the industry temporarily
- The units shall obtain trade license and certificates from Municipal corporations, municipalities, DICs as applicable
- The unit may join ICEF project for obtaining 50% reimbursement through submission of financial application